Conversing Across the Divide: An Meeting Between Different Perspectives
-
- By Roy Porter
- 08 May 2026
On one of the busiest tourist streets in the core of Scotland's historic capital stands a giant structure of construction framework.
For the past 60 months, a prominent hotel on the intersection of the famous Royal Mile and George IV Bridge has been a covered eyesore.
Visitors find no available accommodations, pedestrians are squeezed through confined passages, and establishments have vacated the building.
Restoration efforts began in 2020 and was initially projected to last a few months, but now fed-up residents have been told the scaffolding could persist until 2027.
Sir Robert McAlpine (SRM), the main contractor, says it will be "towards the end" of 2026 before the initial parts of the frame can be taken down.
Edinburgh's council leader a council official has labeled it a "blight" on the area, while conservationists say the work is "extremely disruptive".
What is transpiring with this seemingly endless project?
The establishment with 136 rooms was built on the site of the former regional authority offices in 2009.
Figures from when it first opened under the Missoni Hotel banner, put the build cost at about a significant sum.
Remedial efforts began not long after the start of the global health crisis with the hotel itself shut for business since 2022.
A lane of traffic and a sizable stretch of sidewalk leading up to the junction of the historic street have been closed off by the project.
Pedestrians going to and from the an adjacent district and another locale have been required one after another into a tight, enclosed passage.
An eatery Ondine quit the building and transferred to a different location in 2024.
In a statement, its management said the ongoing project had obliged them to modify the restaurant's appearance, adding that "customers deserved better".
It is also hosts dining franchise a chain – which has placed large notices on the structure to inform customers it is operating as usual.
An update to the a local authority committee in the start of the year suggested that the process of "revealing" the façade would begin in February, with a total takedown by the end of the year.
But the contractor has said that is incorrect, referencing "extremely complex" building problems for the postponement.
"We project starting to dismantle sections of the structure near the finish of 2026, with subsequent enhancements ongoing after that," a statement read.
"Efforts are underway closely with all parties to ensure we create an enhanced site for the public."
A heritage director, head of heritage body the Cockburn Association, said the work had added to the city's reputation of being "slow" for development.
She said those working on the project had a "public duty" to minimise disturbance and should integrate the work into the city's aesthetic.
She said: "It is making the walking experience in that area of the city really difficult.
"I don't understand why there is not a try to integrate it into the urban landscape or produce something more aesthetic and cutting-edge."
A company representative said work on "ideas to enhance the appearance the site" was ongoing.
They continued: "We recognize the frustrations felt by the community and shops.
"This constitutes a long and drawn-out process, demonstrating the difficulty and magnitude of the repair work required, however we are dedicated to concluding this vital work as soon as is possible."
Ms Meagher said the local authority would "continue to put pressure" on those accountable to finish the project.
She said: "This framework has been a negative presence for years, and I understand the frustration of inhabitants and local businesses over these persistent hold-ups.
"That said, I also acknowledge that the contractor has a obligation to make the building safe and that this remediation has proved to be hugely complex."
A seasoned casino analyst with over a decade of experience in gaming strategies and industry trends.